Lakelands Swim School

Lakelands Swim School

Engineering – Link Engineering
Building – Focus Building

As an extension to the newly formed Lakelands Shopping Centre the builder engaged CMP to look after the Mechanical Services for this project.

The project consisted of a Roof Mounted (Custom Made) Pool Packaged System designed and installed to provide close control of the pool area temperature and humidity. With the challenges around corrosion CMP had Blygold WA treat all the twin cladded metal duct work to improve the longevity of the equipment. Supply Air into the Pool Area was via a Fabric Duct Sock with a specifically designed air pattern suited to the application.

Toilet and Changeroom Extraction System also had corrosion issues to deal with so all hanging equipment was stainless steel and all ductwork was made from ACW Aluminium Panel Board. The Office also had a Panasonic Ducted Split System servicing that area.

This was our first project with Focus and I was pleased to hear they were happy with the service and quality we provided. Well done again team CMP.

Recent Posts
Contact Us

Customised Mechanical Projects usually reply with 24 hours except for weekends. All emails are kept confidential and we do not spam in any way.

Not readable? Change text. captcha txt